The plan was to install rebar this morning, inspect at noon and pour concrete in the afternoon. Great plan, but the first meeting with the enemy (you know the story). The rebar was put in the ground, but the verticals were not installed per print, so the inspector gave us the thumbs down and gave us permission to try again. With additional rebar installed (18" OC vice 36" OC), we plan to have the reinspect done on Monday morning and pour concrete in the afternoon.