Friday, October 25, 2013

Day 22 (October 25)

Today, we reached 66% of the objectives for the day.  The "plan" was to install rebar starting at 0730, inspect at 0900, and pour in the late morning.  After meeting with reality, the execution looked more like start work at 0930, start installing rebar at 1000.  Finish installing rebar at 1430 and complete the inspection for the pour at 1600.  Frankly, we were fortunate to get the inspection done.  The inspector was initially scheduled for 0900, then renegotiated to 1200, then finally the last slot of the day.

In order to catch up the plan is to pour concrete at 0900 tomorrow (Saturday).  Hmmm!  I want to see this one carried off.  I will be there to watch.

One thing of note.  As you can see from the pictures, there is quite a bit of rebar going into this patio.  Apparently, this is the commercial patio arrangement--it will certainly support a hot tub. 

It was interesting to see this constructed.  Once the plans were reviewed thoroughly, it was off to the hardware store for more rebar. 

I will provide pictures of before and after rebar to the GC tomorrow so that he understands that the time of completion estimates that he has been getting from his subs have been gloriously optimistic.